Dormitories

Local Family Organizes Benefit Run for CWS

Memorial Run for Alana & Chrissy Saturday, October 22, 2011 10K begins at 8:00am 5K begins at 9:00am Fun Walk begins at 10:15am Pre-registration preferred; however, registration will begin 1 hour prior to each event. Registration via mail received by October 8, 2011 will ensure t-shirt. All proceeds go to Camp Willow Springs in Memory of Alana Liles and Chrissy Laureano For more details, click here to download the registration form.

Interior Work Continues…

Painting and sub-contractor work has continued in both dormitories.  The addition of counter tops, sinks, shower stalls, and toilets bring the two buildings closer and closer to completion. As this work continues, the YCFC Board of Directors is making plans for how to proceed with development of Phase One.

Tile & Grout

The tile and grout work is nearly finished in one of the dormitories.

CWR Office Field Trip!

On Friday the Camp Willow Run staff closed the office for a few minutes to visit the Camp Willow Springs site.   There was a lot of excitement as the staff saw the dormitories and walked through them imagining the day that children would be there for summer camp.  The visit concluded with a special time of prayer thanking the Lord for His faithfulness and seeking His guidance in completing Camp Willow Springs.

Timelapse of both dormitories

Below is a video showing the progress made on the two dormitories this year.   Timelapse of the Two Dormitories from Camp Willow Run on Vimeo.

Five Months in Eleven Seconds

Check out the video below of the progress made on one of the dormitories!   Five Months in 11 Seconds from Camp Willow Run on Vimeo.

Dormitories are even closer…

The exterior paint is done and the electrical work is complete in both dormitories.  The interior painting is finished in one dormitory and will soon be compete in the other.  Tile in the bathrooms will soon be laid.

Interior & Exterior Painting

The exterior painting is nearly complete and the interior painting is underway.

Exterior Paint

After considering a few samples, a paint color has been decided and painting is now underway!

Grading

The ground around the dormitories is being graded so that it may then be seeded.  Once this is complete exterior painting will begin.