• Progress on Septic System

    The work site has finally dried out enough that work can continue on the septic system and two dormitories.  Final preparations are being made to be able to pour the concrete for the dormitories. The septic system for the office and healthcare center are being installed and the water should be connected to the buildings soon. You can check out pictures on the Camp Willow Springs facebook page: http://www.facebook.com/campwillowsprings .  

  • Utility Installation

    Ellington Contractors worked Friday and Saturday to trench and lay conduit for the utility installation for Phase One of Camp Willow Springs.  Their work will allow us to soon have electrical power at the construction site.  The Ellington brothers, David, Matt, and Michael, were all campers at Camp Willow Run in the 80’s and 90’s.  David’s sons, Kyle and Jake, who are current campers, joined their dad for the weekend.

  • Dormitory Footers & Access Road

    E. Carroll Mann Contractors is digging the footings of the two dormitories and Glover Construction is on site to complete the graveling of the entry road and parking lot.  Also, they installed and graveled the access road to the dorm construction site. We praise the Lord for those who are partnering with us to see CWS become a reality.   This is a great day!

  • Great is His Faithfulness

    We serve an amazing God.  Great is His faithfulness. Every day we are truly awed by the changes being sculptured in the land through the site preparation at Camp Willow Springs!  Eleven earthmoving machines are on site shaping the new entrance road and parking area, defining the location of the dining hall and the areas for the girl’s dormitories, boy’s dormitories, the Aquatic Center, the Amphitheater, Health Care Center, Campstore, office, and meeting room. Watch the progress and grow with us in the inspiring development of Camp Willow Springs!

  • Site Development Has Begun

    “Behold, I will do something new.  Now it will spring forth…..”       Isaiah 43: 19a After a long and very busy twenty-four months of working with Engineers, Surveyors, a Soil Scientist, Site Contractors, Building Contractor and State and County officials, it is with excitement that we have this update to share with you. The plan for grading, soil erosion and sediment control has been completed by our Engineers and approved by the State of North Carolina.  The Surveyor is completing the staking for all site plan needs (buildings, roads, parking, septic, etc). Designs of buildings are being finalized for presentation to our County officials for permitting.  And on Tuesday, July 14,…