Dormitory Progress
The beautiful weather has allowed E. Carroll Mann Contractors to make noticeable progress on the construction of the two dormitories. The exterior and interior walls have been framed on one building. Framing is now underway on the second building. Each dormitory will be 2,100 square feet. It is exciting to see the dormitories take shape!
-
Pictures
-
Dormitory Picture Update
-
Utility Installation
Ellington Contractors worked Friday and Saturday to trench and lay conduit for the utility installation for Phase One of Camp Willow Springs. Their work will allow us to soon have electrical power at the construction site. The Ellington brothers, David, Matt, and Michael, were all campers at Camp Willow Run in the 80’s and 90’s. David’s sons, Kyle and Jake, who are current campers, joined their dad for the weekend.
-
Concrete Poured Today
After having some delays due to rain this week, the concrete is finally being poured today. It is exciting to see the big concrete trucks coming down the road. There is a crew here now. They have almost finished the first dormitory and should be moving on to the second one shortly.
-
Ready for Concrete
Today, Wayne Powell of Roanoke Valley Exterminating treated both dorm sites. The plastic vapor barrier has now been laid, preparing the way for concrete to be poured next Tuesday. We are thankful for the beautiful weather that we have had this week!
-
Plumbing
The plumbing has been roughed-in and passed inspection. If weather permits, we hope to pour the concrete slabs early next week.
-
Gravel Backfill
-
Foundation Blocks
The foundation blocks have been completed and are ready for the gravel backfill.
-
Footings Poured
The footings have been poured and the foundation blocks will soon be laid.